A project team has been arguing for days about the correct way to complete a high level design. This has caused the SPI to fail to 0.89 and has a CPI of 0.9. If the project manager tees the team “we will schedule this discussion for our team meeting next week”. The project manager is ______ .
A.using earned value
B.compromising
C.increase costs even further
D.withdrawing