The most crucial time for project risk assessment is______.

A. when a problem surfaces
B. during the planning phase
C. during the close-out phase
D. after the project schedule has been published

答案

参考答案:B

解析: 进行项目风险评估最关键的时候是:规划阶段(during the planning phase)。
选项A:问题出现时。选项C:结束阶段。选项D:项目进度公布之后。