问题 写作题

写作(共10分)

人们完成工作的方式通常有两种:独立完成与合作完成。两种方式各有特点。请你以“Working Individually or Working in a Team”为题,按照以下要点写一篇英语短文:

1.独立完成:自行安排、自己解决问题

2.合作完成:一起讨论、相互学习

3.我喜欢的方式及理由

注意:词数100~120,文章的题目和开头已给出(不计词数)。

Working Individually or Working in a team

There are basically two ways to get work done._______________________

答案

Working Individually or Working in a team

There are basically two ways to get work done. One is to work individually. In this way, people can decide for themselves when to start work and how to do it. What’s more, they will be able to learn how to solve problems on their own.

People may also choose to work in a team, where they can learn from each other and help each other. Besides, they may work out better ways to get work done by discussion.

Personally, I prefer to work in a team, which offers me a chance to learn how to get along with others and to share my experiences with them. As the work can be divided among several people, it can be done efficiently. Teamwork is always important.

问答题

试题一(25分) 阅读下列说明,回答问题1至问题3,将解答填入答题纸的对应栏内。 [说明] A公司是一家专门从事系统集成和应用软件开发的公司,目前有员工100多人,分属销售部、软件开发部、系统网络部等业务部门。公司销售部主要负责服务和产品的销售工作,将公司现有的产品推销给客户,同时也会根据客户的具体需要,承接信息系统集成项目,并将其中应用软件的研发任务交给软件开发部实施。 经过招投标,A公司承担了某银行的系统集成项目,合同规定,5月1日之前系统必须完成,并且进行试运行。合同签订后,项目的软件开发任务由软件开发部负责,硬件与网络由系统网络部负责设计与实施。王工担任这个项目的项目经理。王工根据项目需求,组建了项目团队,团队分成软件开发小组和网络集成小组,其中软件开发小组组长是赵工,网络集成小组组长是刘工。王工制定了项目进度计划,图1是该项目的进度网络图。

图1中各个活动的工期在表1中列出。

 软件开发中,发现有两个需求定义得不够明确,因此增加了一些功能,导致功能模块设计延长了五天。网络集成过程中,由于涉及物联网等新技术,综合布线延迟了五天,接着采购的一个新设备没有按时到货,到货之后在调试过程中遇到了以前没有遇到的问题,使网络设备安装调试延迟了7天。两个小组分别通过电话向各自部门通报项目进展,而网络集成工作是在用户现场进行的,因此网络集成的进度状况在公司总部进行开发工作的软件开发小组并不了解。上述问题导致了项目整体进度的拖延,绩效状况不佳。

分析案例中发生问题的可能原因。