问题 单项选择题

In the dining room of my grandfather’ s house stood his heavy clock. Meals in the dining room were a (21) for our four generations to become one. My grandfather’ s clock always stood like a trusted old family friend, (22) us playing jokes and tellingstories, which was already a (23) of our life.

When I was a child, the old clock interested me. I watched and listened to it during (24) I was surprised how at (25) times of the day, the clock would strike three times, six times or more, with a wonderful great (26) that echoed throughout the house. The clock chimed year after year, a part of my (27) , a part of my heart.

Even more (28) to me was my grandfather’s special action each day. He meticulously (29) the clock with a special key each day. The key was magic to me. It (30) our family’ s magnificent clock ticking and striking all year round.

28()

A.stories 

B.jokes 

C.periods 

D.meals

答案

参考答案:D

解析:

根据上一段内容及生活常识可知,当我们在听故事或开玩笑的时候很难 留意到其他事物,C项在文中没有依据,D项最为恰当。

问答题

(三) 某办公楼工程,建筑面积82000m2,地下3层,地上20层,钢筋混凝土框架一剪力墙结构,距邻近六层住宅楼7m。地基土层为粉质黏土和粉细砂,地下水为潜水,地下水位-9.5m,自然地面-0.5m。基础为筏板基础,埋深14.5m,基础底板混凝土厚1500mm,水泥采用普通硅酸盐水泥,采取整体连续分层浇筑方式施工。基坑支护工程委托有资质的专业单位施工,降排的地下水用于现场机具、设备清洗。主体结构选择有相应资质的A劳务公司作为劳务分包,并签订了劳务分包合同。

合同履行过程中,发生了下列事件。

事件1:基坑支护工程专业施工单位提出了基坑支护降水采用“排桩+锚杆+降水井”方案,施工总承包单位要求基坑支护降水方案进行比选后确定。

事件2:底板混凝土施工中,混凝土浇筑从高处开始,沿短边方向自一端向另一端进行,在混凝土浇筑完12h内对混凝土表面进行保温保湿养护,养护持续7d。养护至72h时,测温显示混凝土内部温度70℃,混凝土表面温度35℃。

事件3:结构施工到10层时,工期严重滞后。为保证工期,A劳务公司将部分工程分包给了另一家有相应资质的B劳务公司,B劳务公司进场工人100人。因场地狭小,B劳务公司将工人安排在本工程地下室居住。工人上岗前,项目部安全员向施工作业班组进行了安全技术交底,双方签字确认。

指出事件2中底板大体积混凝土浇筑及养护的不妥之处,并说明正确做法。