问题 单项选择题

Software engineering is the science and art of specifying, designing, implementing, and (66) with economy, timeliness and elegance, programs, (67) and operating procedures whereby computers can be made useful to humanity.

This definition implicitly sets (68) the basic goal of software engineering research and development: The basic goal of software engineering is to facilitate specification, design, implementation and evolution of programs, documentation and operating (69) which are useful to humanity in an economic, (70) and elegant manner (using the appropriate science and art).

(68)处填()。

A.out

B.in

C.of

D.with

答案

参考答案:A

单项选择题
问答题

某城市地下工程,业主与施工单位参照FIDIC合同条件签订了施工合同,除税金外的合同总价为8600万元,其中:现场管理费率15%,企业管理费率8%,利润率5%,合同工期730天。为保证施工安全,合同中规定施工单位应安装满足最小排水能力1.5t/min的排水设施,并安装1.5t/ min的备用排水设施,两套设施合计15900元。合同中还规定,施工中如遇业主原因造成工程停工或窝工,业主对施工单位自有机械按台班单价的60%给予补偿,对施工单位租赁机械按租赁费给予补偿(不包括运转费用)。

该工程施工过程中发生以下三项事件。

事件1:施工过程中业主通知施工单位某分项工程(非关键工作)需进行设计变更,由此造成施工单位的机械设备窝工12天。

事件2:施工过程中遇到了非季节性大暴雨天气,由于地下断层相互贯通及地下水位不断上升等不利条件,原有排水设施满足不了排水要求,施工工区涌水量逐渐增加,使施工单位被迫停工,并造成施工设备被淹没。

为保证施工安全和施工进度,业主指令施工单位紧急增加购买额外排水设施,尽快恢复施工,施工单位按业主要求购买并安装了两套1.5t/min的排水设施,恢复了施工。

事件3:施工中发现地下文物,处理地下文物工作造成工期拖延40天;

就以上三项事件,施工单位按合同规定的索赔程序向业主提出索赔。

事件1:由于业主修改工程设计12天,造成施工单位机械设备窝工费用索赔见表4-1所示。

现场管理费:40920元×15%=6138元

企业管理费:(40920+6138)元×8%=3764.64元

利润:(40920+6138+3764.64)元×5%=2541.13元

合计:53363.77元

事件2.由于非季节性大暴雨天气费用索赔:

(1)备用排水设施及额外增加排水设施费:(15900÷2×3)元=23850元

(2)被地下涌水淹没的机械设备损失费16000元

(3)额外排水工作的劳务费8650元

合计:48500元

事件3.由于处理地下文物,工期、费用索赔:

延长工期40天

索赔现场管理费增加额:

现场管理费:8600万元×15%=1290万元

相当于每天:(1290×10000÷730)元/天=17671.23元/天

40天合计:(17671.23×40)元=706849.20元

[问题]

1.指出事件1中施工单位的哪些索赔要求不合理,为什么?监理工程师审核施工单位机械设备窝工费用索赔时,核定施工单位提供的机械台班单价属实,并核定机械台班单价中运转费用分别为:9m3空压机为93元/台班,25t履带吊车为300元/台班,塔式起重机为190元/台班,混凝土泵车为140元/台班,监理工程师核定的索赔费用应是多少?

2.事件2中施工单位可获得哪几项费用的索赔?核定的索赔费用应是多少?

3.事件3中监理工程师是否应同意40天的工期延长?为什么?补偿的现场管理费如何计算,应补偿多少元?