The schedule control process for a project ______ .
A.focuses on starting the project earlier than scheduled
B.is necessary for controlling changes to the project schedule
C.is concerned only with activities that are on the critical path
D.should focus entirely on activities that are difficult to carry out
答案
参考答案:B
解析: 项目的进度控制过程 ______ 。 A) 集中于比预计要早的时间启动项目 B) 对控制项目进度的变更而言是必要的 C) 只关注关键路径上的活动 D) 应该完全集中于那些难以完成的活动上 进度控制过程用来控制针对项目进度的变更。