问题 阅读理解

阅读理解。请根据短文内容选择正确的答案。

      It's a sunny and beautiful day. It's April 3rd. Miss Lee is going to a park. She is going to read some books

there. The air is fresh and the flowers are nice there. Her best friend Mary will go there too. After some reading,

they are going to the clothes shop. They are going to do some shopping. Miss Lee is very pretty. She likes

dresses. She is going to buy a purple dress. But Mary is going to buy a T-shirt. She likes wearing a T-shirt with

jeans. Oh, look! They are coming! They are going to get there on foot. It's not far from here.

1. It's a _____________ and beautiful day.

A. sunny

B. rainy

C. windy

2. Miss Lee is going to a _____________ first.

A. library

B. shop

C. park

3. What is Miss Lee going to buy? She is going to buy a _____________. 

A. T-shirt

B. dress

C. book

4. What is she going to do in the park?

A. Go shopping.

B. Play with Mary.

C. Read books.

5. They are going to get there _____________.

A. on foot

B. by bus

C. by taxi

答案

1. A  2. C  3. B  4. C  5. A

问答题
多项选择题

某施工单位(乙方)与某建设单位(甲方)签订了建造无线电发射试验基地施工合同。合同工期为38天。由于该项目急于投入使用,在合同中规定,工期每提前 (或拖后)1天奖(罚)5 000元。乙方按时提交了施工方案和施工网络进度计划(图5-13),并得到甲方代表的同意。

实际施工过程中发生了如下几项事件。
事件1:在房屋基槽开挖后,发现局部有软弱下卧层。按甲方代表指示,乙方配合地质复查,配合用工为10个工日。地质复查后,根据经甲方代表批准的地基处理方案,增加工程费用4万元,因地基复查和处理使房屋基础施工延长3天,人工窝工15个工日。
事件2:在发射塔基施工时,因发射塔坐落位置的设计尺寸不当,甲方代表要求修改设计,拆除已施工的基础,重新定位施工。由此造成工程费用增加1.5万元,发射塔基础施工延长2天。
事件3:在房屋主体施工中,因施工机械故障,造成工人窝工8个工日,房屋主体施工延长2天。
事件4:在敷设电缆时,因乙方购买的电缆质量不合格,甲方代表令乙方重新购买合格电缆。由此造成敷设电缆施工延长4天,材料损失费1.2万元。
事件5:鉴于该工程工期较紧,乙方在房屋装修过程中采取了加快施工的技术措施,使房屋装修施工缩短3天,该项技术措施费为0.9万元。
其余各项工作持续时间和费用均与原计划相符。

对于合同执行者而言,合同跟踪的对象有( )。

A.承包的任务

B.工程小组或分包人的工程和工作

C.业主和其委托的工程师的工作

D.设计部门的设计变更工作

E.供应商的供应进度和质量