问题 单项选择题

Modern industrial society grants little status to old people. In fact, such a society has a system of built-in obsolescence. There is no formal system for continuing our education throughout our life in order to keep up with rapidly changing knowledge. When our education and job skills have grown obsolete, we are treated exactly like those who have never gained an education or job skills and are not encouraged or given the opportunity to begin anew.As a society becomes more highly developed, the overall status of older people diminishes. Improved health technology creates a large pool of old people, who compete for jobs with the young. However, economic technology lowers the demand for workers and creates new jobs for which the skills of the aged are obsolete, forcing older people into retirement. At the same time, young people are being educated in the new technology and are keeping pace with rapid changes in knowledge. Finally, urbanization creates age-segregated neighborhoods. Because the old live on fixed incomes, they must often live in inferior housing. All these factors — retirement, obsolete knowledge and skills, inferior standards of living — lower the status of the aged in society.A century ago, when one could expect to live only to 50 or so, the life span more or less coincided with the occupation and family cycle. But today the average life span allows for fifteen to twenty years of life after these cycles. It appears that our life span is outpacing our usefulness in society.

According to the first paragraph, which of the following is true

A.People don’t have to gain education.

B.People don’t have to learn job skills.

C.People don’t have to be treated as equals.

D.People don’t have chances to begin anew.

答案

参考答案:D

解析:是非题型。根据第一段第四句When our education and job skills have grown obsolete,we are treated exactly like those who have never gained an education or job skills and are not encouraged or given the opportunity to begin anew.一旦我们的教育和技能落后了,就没有受教育、学技能的机会了,也就没有重新再来的机会了。

问答题

某工程项目业主与施工单位签订了施工合同。施工合同中规定,除空间钢桁架屋盖可分包给专业工程公司外,其他部分不得分包(除非业主同意)。本项目合同工期为22个月。

在工程开工前,施工单位在合同约定的日期内向工程师提交了施工总进度计划(见下图)和一份工程报告。

工程报告的主要内容如下:

(1)鉴于本项目需要安装专业的进口设备,需要将设备安装工程分包给专业安装公司。

(2)本项目两侧临街,且为繁华交通要道,故需在施工之前搭设遮盖式防护棚,以保证过往行人安全。此项费用未包含在投标报价中,业主应另行支付。

工程师对施工单位提交的施工进度计划和工程报告进行了审核。施工单位在按工程师确认的进度计划施工0.5个月后,因业主要求需要修改设计,致使工作K(混凝土工程)停工2.5个月。设计变更后,施工单位及时通过工程师向业主提出索赔申请(见下表)。

索赔申请

在施工过程中,部分施工机械由于运输原因未能按时进场,致使工作H的实际进度在第12月底时拖后1个月。

在工作F进行过程中,发生质量事故,工程师下令停工,组织召开现场会议,分析事故原因。该质量事故是由于施工单位施工工艺不符合施工规范要求所致。工程师责成施工单位返工,工作F的实际进度在第12月底时拖后1个月。

问题

施工单位在索赔申请表中所列的内容和数量,经工程师审查后均属真实,但费用计算有不妥之处,请说明费用计算不妥的项目及理由。

单项选择题