问题 完形填空

任务型阅读(共10分,每题2分)

Pets are a part of people’s lives. Some pets are like family. In these days, many people have pets at home and spend a lot of money improving their lives. In fact, in some parts of the world, pets get real VIP treatment(待遇). VIP usually means Very Important People, but here VIP means Very Important Pets!

When you want to give Fido or Kitty a holiday, or when you are going away on business, you can put them at a dog and cat hotel, and cats have a large place with something to climb on and play with. The guests get the best food during their stays at these hotels.

There are other special services(服务) at  hotels. Imagine you are traveling and you want to see your pet: the hotel can put a video camera in the pet’s room. So you can see your Fido or Kitty on TV.

The hotels usually have good groomers(美容师): They often bath and take the best hair care for the pets. But you need to make an appointment because people are usually very busy taking care of pets.

小题1:What’s the new meaning of “VIP” in this passage?

                               

小题2:According to this passage, where can you put your pet when you are away on business?

                                                                     

小题3:What does “Fido” stand for(代表) here?

                                        

小题4:How can you see your pet during your traveling?

                                                                     

小题5:Why need you make an appointment when you want a good groomer for your pet?

                                                          

答案

小题1:Very Important Pets.

小题1:A dog and cat hotel.

小题1:A dog / A pet.

小题1:On TV / By a video camera.

小题1:Because they are usually very busy.

问答题

某工程项目,业主通过招标与甲建筑公司签订了土建工程施工合同,包括A、B、C、D、E、F、G、H八项工作,合同工期360天。业主与乙安装公司签订了设备安装施工合同,包括设备安装与调试工作,合同工期180天。通过相互的协调,编制了如下图所示的网络进度计划:

该工程施工过程中发生了以下事件:

事件1:基础工程施工时,业主负责供应的钢筋混凝土预制桩供应不及时,使A工作延误7天。

事件2:B工作施工后进行检查验收时,发现预埋件埋没位置有误,经核查,是由于设计图纸中预埋件位置标注错误所致。甲建筑公司进行了返工处理,损失5万元,且使B工作延误15天。

事件3:甲建筑公司因人员与机械调配问题造成C工作增加工作时间5天,窝工损失2万元。

事件4:乙安装公司设备安装时,因接线错误造成设备损坏,使乙安装公司安装调试工作延误5天,损失12万元。

发生以上事件后,施工单位均及时向业主提出了索赔要求。

问题:

1.施工单位对以上各事件提出索赔要求,分析业主是否应给予甲建筑公司和乙安装公司工期和费用补偿。

2.如果合同中约定,由于业主原因造成延期开工或工期延期,每延期一天补偿施工单位6000元,由于施工单位原因造成延期开工或工期延误,每延误一天罚款6000元。计算施工单位应得的工期与费用补偿各是多少。

3.该项目采用预制钢筋混凝土桩基础,共有800根桩,桩长9米。合同规定:桩基分项工程的综合单价为180元/米;预制桩由业主购买供应,每根桩按950元计。计算甲建筑公司桩基础施工应得的工程款是多少。

(注:计算结果保留一位小数。)