业主对工程项目管理的根本目的是()。
A.按合同规定取得合法收入
B.保证资金的安全性
C.实现投资者的投资目标和期望
D.保证工程项目建成后在项目功能与质量上达到设计的质量标准
E.使工程项目投资控制在预定或可接受的范围之内