问题 单项选择题

Anthropology is the study of human beings as creatures of society. It (1) its attention upon those. physical characteristics and industrial techniques, those conventions and values, which (2) one community from all others that belong to a different tradition.

The distinguishing mark of anthropology among the social sciences is that it includes for serious study other societies (3) our own. For its purposes any social (4) of mating and reproduction is as significant as our own. To the anthropologist our customs and those of a New Guinea tribe are two possible social schemes for (5) a common problem, and in so far as he remains an anthropologist he is (6) to avoid any weighting of one (7) the other. He is interested in human behavior, not as it is shaped by one tradition, our own, but as it has been shaped by any tradition (8) He is interested in a wide (9) of custom that is found in various cultures, and his object is to understand the way in which these cultures change and (10) , the different forms through which they express themselves and the (11) in which the customs of any peoples function in the lives of the (12) .

Now custom has not been commonly regarded as a (13) of any great moment. The inner workings of our own brains we feel to be uniquely (14) of investigation, but custom, we have a way of thinking, is behavior at its most commonplace. (15) , it is the other way round. Traditional custom is a mass of detailed behavior more astonishing than (16) any one person can ever evolve in individual actions. Yet that is a rather (17) aspect of the matter. The fact (18) first rate importance is the predominant role that custom (19) in experience and belief, and the very great varieties it may (20)

2()

A.distinguish

B.prohibit

C.dispel

D.exempt

答案

参考答案:A

解析:

distinguish A from B“使A区别于B”。其他选项词义和用法举例分别为:[B]prohibit“禁止,阻止”,如:prohibit sb. from doing sth.“禁止某人做某事”;[C]dispel“驱散,驱逐”,如:dispel the notion“去除某观念”;[D]exempt“免除”,如:exempt sb. from military service“使某人免除服兵役”。

多项选择题
多项选择题

某建设项目在施工过程中发生了以下3个事件。

事件1:该建设项目的业主提供了地质勘查报告,报告显示地下土质很好,承包商依此作了施工方案,拟用挖方余土作通往项目所在地道路基础的填方。由于开挖施工时正值雨季,开挖后土方潮湿,易于破碎,不符合道路填筑要求。承包商不得不将余土外运,另外取土作道路填方材料。

事件2:该工程按月规定的总工期计划,应于某年某月某日开始现场搅拌混凝土。因承包商的混凝土搅拌设备迟迟不能运往工地,承包商决定使用商品混凝土,但被业主否决。而在承包合同中未明确规定使用何种混凝土。承包商不得已,只有继续组织混凝土搅拌设备进场,由此导致施工现场停工,工期拖延和费用增加。

事件3:该工程设有地下室,属于隐蔽工程,该工程施工过程中,工程师对已同意承包人覆盖的隐蔽工程质量有怀疑,指示承包人进行重新检验,检验结果表明该部分施工质量未达到合同约定的质量标准,但满足行业规范的要求。

施工承包合同中规定应由承包人自行承担责任的情况有()。

A.经工程师确认的施工组织设计和工程进度计划本身存在缺陷

B.因工程师不及时作出答复,导致承包人无法复工

C.影响施工正常进行的检查检验,检查检验结果不合格

D.由于承包人原因造成的工程停工