问题 单项选择题

Developing the project schedule is often an iterative process.It determines the planned start and finish dates for project activities and milestones.Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to ______ progress.

A.analyze
B.track
C.level
D.extend

答案

参考答案:B

填空题
判断题