A manufacturing project has a schedule performance index(SPI)of 0.89 and a cost performance index(CPI)of 0.91.Generally,what is the BEST explanation for why this occurred ?()
A.The scope was changed
B.A supplier went out of business and a new one needed to be found
C.Additional equipment needed to be purchased
D.A critical path activity took longer and needed more labor hours to complete