In risk response planning,you are in the process of developing options,and determining actions to reduce threats to your project’s objectives.When you show the results of your risk response planning to your project sponsor,she is not comfortable with the risks in the project and she suggests that the project scope should be decreased.This is an example of______.

A.inappropriate risk management because it is having a direct impact on your project scope

B.risk avoidance

C.risk mitigation

D.risk transfer

答案

参考答案:B

解析: 在风险应对规划中,你在研究可选方案,以减低对你项目目标造成影响的威胁。当你展示规划风险应对给你的项目干系人看时,她不满意并建议减小项目范围。这是一个______的例子。 A) 不恰当的项目风险管理(因为这会对项目范围产生直接影响) B) 风险回避 C) 风险缓解 D) 风险转移 在风险应对策略分析中,风险回避是通过修改项目管理计划;风险缓解是通过降低发生概率或影响;风险转移是将风险转移给第三方。