______ is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. The key benefit of this process is that it allows the scope baseline to be maintained throughout the project.

A.Collect Requirements
B.Validate Scope
C.Control Scope
D.Create WBS

答案

参考答案:C

解析: 控制范围(Control Scope)是监督项目和产品的范围状态,管理范围基准变更的过程。本过程的主要作用是,在整个项目期间保持对范围基准的维护。