问题 单项选择题

Within the last fifty years, the majority of the United States work force has moved from the manufacturing to the service sector of the economy. This shift has occurred, not because of a decline in the production of goods, but because, with applications of new technology, more production of goods can now be achieved with relatively fewer people, and more people are therefore available to satisfy the increased demand for services.
Which of the following, if true, provides evidence to support the claim made above that more production of goods can now be achieved with relatively fewer people

A.Many manufacturing industries in the United States have lost a significant share of their domestic and foreign markets to foreign producers.

B.Services accounted for half of all jobs in the late 1940’s but today account for seventy percent of all jobs.

C.Manufacturing output was one-third higher in 1980 than in 1970, while manufacturing employment grew only five percent during that period.

D.Manufacturing industries, on average, pay a higher perhour wage and use fewer part-time employees than do service industries.

E.(E) Living standards in states that have shifted to manufacturing economies within the last fifty years are closer to the national average now than in 1940.

答案

参考答案:C

解析: 本题支持的内容非常明确,已在问题目的中清晰列出,即让我们找一个选项说明确实“更多的物质生产可由相对较少的人完成”,读完问题目的马上可以理解答案内容。(C)说明1980年比1970年高出1/3,而就业人数只高出5%,实现了问题目的,所以(C)正确;(B)易误选,但(B)并不能表明“更多的物质生产可由相对较少的人完成”;(A)、(D)、(E)均无法实现问题目的。

问答题

某工程项目,经有关部门批准采取公开招标的方式确定了中标单位并签订合同。 该工程合同条款中部分规定如下:

(1)由于设计未完成,承包范围内待实施的工程虽然性质明确,但工程量还难以确定,双方商定拟采用总价合同形式签订施工合同,以减少双方的风险。

(2)施工单位按建设单位代表批准的施工组织设计(或施工方案)组织施工,施工单位不承担因此引起的工期延误和费用增加的责任。

(3)建设单位向施工单位提供场地的工程地质和地下主要管网线路资料,供施工单位参考使用。

(4)施工单位不能将工程转包,但允许分包,也允许分包单位将分包的工程再次分包给其他施工单位。

在施工招标文件中,按工期定额计算,该工程工期为573天。但在施工合同中,双方约定:开工日期为2008年12月15日,竣工日期为2010年7月25日,日历天数为586天。

在工程实际实施过程中,出现了下列情况:

工程进行到第6个月时,国务院有关部门发出通知,指令压缩国家基建投资,要求某些建设项目暂停施工。该工程项目属于指令停工下马项目,因此,业主向承包商提出暂时中止合同实施的通知。承包商按要求暂停施工。

复工后在工程后期,工地遭遇当地百年罕见的台风的袭击,工程被迫暂停施工,部分已完工程受损,现场场地遭到破坏,最终使工期拖延了2个月。

该工程合同条款中约定的总价合同形成是否恰当并说明原因。