问题
单项选择题
The Estimate Activity Resource process is closely coordinated with the ______ process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
答案
参考答案:A
The Estimate Activity Resource process is closely coordinated with the ______ process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
参考答案:A