Your project is very critical for the company and must be completed within 6 months. The project charter has been signed, but scope statement is not yet prepared. Management asks you to go ahead with the project without the scope statement being approved. What should you do(select the best answer)
A.Refuse to work on the project because management is not following standard project management practice
B.Since time is of essence, you should start the project with the inputs from project charte
C.Meet the management and mention the problems you will face without a scope statemen
D.Escalate the issue to the project sponsor and issue a risk mem