问题
多项选择题
施工图预算编制方法有()。
A.实物金额法
B.实物量法
C.费用单价法
D.单价法
E.基价法
答案
参考答案:B, D
施工图预算编制方法有()。
A.实物金额法
B.实物量法
C.费用单价法
D.单价法
E.基价法
参考答案:B, D
阅读理解。 | |
| |
1. If a Canadian who is on a 7-day trip to New York buys $ 800 CAN worth of goods, how much should he pay tax on when returning home? | |
[ ] | |
A. $ 800 CAN B. $750 CAN C. $ 400 CAN D. $ 50 CAN | |
2. For an American citizen on a 2-day tour of Canada, how much tax does he have to pay on $ 1.600 US worth of purchases when returning to the US? | |
[ ] | |
A. $ 24 US B. $ 48 US C. $52 US D. $ 200 US | |
3. What documentation should a couple with a 7-year-old child carry when they drive a car from Canada to America? | |
[ ] | |
A. A BC driver's license, an Air NEXUS card, and a birth certificate. B. An Air NEXUS card, a U.S. Coast Guard Merchant Marine Document, and a birth certificate. C. Two valid passport cards and a certified copy of a birth certificate. D. A NEXUS card, a U.S. Coast Guard Merchant Marine Document, and a certified copy of a birth certificate. |