问题 单项选择题

Project()Management includes the processes required to ensure that theproj ect includes all the work required, and only the work required, to complete the project successfully.

A.Integration

B.Scope

C.Configuration

D.Requirement

答案

参考答案:B

解析:

该题的关键词为"all the work required, only the work required",其语句结构为"Project()Management(主语)includes(谓语)the processes",含义为"项目什么管理包含过程",仅根据关键词便可判断出应该与项目范围管理紧密相关,在结合语句分析,应该选择项目范围管理,即Scope。