Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

A.crashing the schedule

B.performing resource leveling

C.conducting reverse resource allocation scheduling

D.utilizing the critical chain resources

答案

参考答案:A