问题 单项选择题

Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.

A.PERT

B.Resourceleveling

C.Schedulecompression

D.Critical chain method

答案

参考答案:D