问题 单项选择题

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.

A.10

B.45

C.50

D.100

答案

参考答案:B