The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

A.Planning

B.Executing

C.Monitoring and Controlling

D.Closing

答案

参考答案:B

解析:

该题的关键词为"accomplish the project's requirements",其语句结构为"The()Process Group(主语)consists of(谓语)the processes used to complete the work defined",含义为"用于完成工作的过程组成什么过程组",所以可知重点描述为"完成工作",根据项目管理五个过程组的特点,选择Executing(执行)过程组,其他选项容易排除。