问题 单项选择题

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

A.milestone

B.baseline

C.quality

D.work

答案

参考答案:D

解析:

该题的关键词为"required resource types、estimated resource quantities、 resource calendars",其语句结构为"Estimating activity durations(主语)uses(谓语)information on activity scope of_____(宾语)",含义为"估算活动工期应用什么活动范围的信息",结合前面的关键词,此处应该识别出估算活动工期对应的输入项,因而选择工作范围,选择选项D。