On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and()are so tightly linkedthat they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.time estimating
B.cost estimating
C.project planning
D.schedule development
参考答案:D
解析:
该题的关键词为"activitysequencing. activity resourceestimating. Activityduration estimating",其语句结构为"activity sequencing, activity resource estimating, activity duration estimating, and (主语)are so tightly linked(谓语)",含义为"活动排序、活动资源估算、活动工期估算以及什么紧密相关",该题考察的知识点在于项目进度管理包含的各个子过程,依次为活动定义、活动排序、活动资源估算、活动工期估算、制定进度计划以及进度监控。考生在了解知识点的前提下能够轻松选出选项D,考生如果缺乏相应的知识,则只能碰运气了。