()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.

A.Plannedvalue

B.Earned value

C.Actualcost

D.Costvariance

答案

参考答案:B

解析:

该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。