()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.Plannedvalue
B.Earned value
C.Actualcost
D.Costvariance
答案
参考答案:B
解析:
该题的关键词为"budgeted amount for the work actually completed",其语句结构为"()(主语)is(谓语)the budgeted amount for the work actually completed",含义为"什么是实际完成工作对应的预算",容易判断该语句正是挣值( Earned value)的定义。