The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
答案
参考答案:D
解析:
该题的关键词为"authority to apply organizational resources",其语句结构为"The____(主语)provides(谓语)the project manager with the authority to apply organizationalresources",含义为"什么为项目经理提供了使用组织资源的权力",根据项目管理知识,为项目经理授权的文件为项目章程,所以应该选择选项D,其他选项容易排除。