某工程分4段,按甲、乙、丙、丁4个施工过程进行施工,有关施工参数见下表所列,则该工程施工的总工期为( )天。
施工过程 | 流水节拍 | |||
一段 | 二段 | 三段 | 四段 | |
甲 | 2 | 3 | 4 | 4 |
乙 | 3 | 2 | 3 | 4 |
丙 | 2 | 4 | 2 | 4 |
丁 | 4 | 3 | 2 | 2 |
A.18
B.23
C.24
D.48