The WBS, estimates for each work package, and the network diagram are completed. Which of the following would be the NEXT thing for the project manager to do
A) Sequence the activities.
B) Verify that they have the correct scope.
C) Create a preliminary schedule and get the team's approval.
D) Complete risk management.
答案
参考答案:C
解析: WBS每个工作包的估算和网络图都已经完成。接下来项目经理应该做什么
A) 活动排序。
B) 检查范围是否正确。
C) 创建初步的进度表并获得团队成员认可。
D) 完成风险管理。
题干表明已经完成排序、估算活动资源、估算活动历时,接下来需要制定进度表。