问题 单项选择题

Which of the following is the most common non-behavioral reason for projects being completed behind schedule and going over budget

A) Selecting a wrong person as the project manager.
B) Selecting a wrong person as the sponsor.
C) Accepting a high-risk project.
D) Inadequately defined requirements.

答案

参考答案:D

解析: 下列哪项是最常见的导致项目进度落后、成本超支的非行为原因
A) 选择了错误的人当项目经理。 B) 选择了错误的人当发起人。
C) 接受了高风险的项目。 D) 不适当的需求定义。
需求如果没有定义好,范围如果不明确,会导致项目出最大的问题。