问题 写作题

根据中文意思和英文提示词语,写出四句语法正确、意思连贯的话。

有一天早晨,彼得发现了什么?他做了什么?后来呢?

1. one early morning, Peter, find, his chair, dirty

2. change, his chair, with Lucy's

3. when ,Lucy, see the dirty chair, just clean it, carefully

4. Peter's face, turn red, and, he, go up to help her

____________________________________________________________________

____________________________________________________________________

____________________________________________________________________

答案

One possible version

(1) One early morning, Peter found his chair very dirty.

(2) He changed his chair with Lucy's.

(3) When Lucy saw the dirty chair, she just cleaned it carefully.

(4) Peter's face turned red and he went up to help her.

问答题

[说明] 系统集成商XX公司承担了某科研机构的信息系统集成项目,建设内容包括应用软件开发、软硬件系统的集成等工作。
在项目建设过程中,由于项目建设单位欲申报科技先进单位,需将此项目成果作为申报的重要内容之一,在合同签订后30天内,建设单位向XX公司要求总工期由10个月压缩到6个月,同时增加部分功能点。
由于此客户为XX公司的重要客户,为维护客户关系,XX公司同意了建设单位的要求。为了完成项目建设任务,XX公司将应用软件分成了多个子系统,并分别组织开发团队突击开发,为提高效率,尽量采用并行的工作方式,在没有全面完成初步设计的情况下,有些开发组同时开始详细设计与部分编码工作;同时招聘了6名应届毕业生加入开发团队。
在项目建设过程中,由于客户面对多个开发小组,觉得沟通很麻烦,产生了很多抱怨,虽然XX公司采取了多种措施来满足项目工期和新增功能的要求,但项目还是频繁出现设计的调整和编码工作的返工,导致项目建设没有在约定的6个月工期内完成,同时在试运行期间系统出现运行不稳定情况和数据不一致的情况,直接影响到建设单位科技先进单位的申报工作;并且项目建设单位对XX公司按合同规定提出的阶段验收申请不予回应。

结合本试题所述项目工期的调整,请简述XX公司应按照何种程序进行变更管理。