Upon completing a project schedule, Roberta finds the critical path indicates the project will complete on April 15. As she works through the schedule, she finds there are several tasks with float. Task B has 10 days of free float, while Task F has 5 days of total float. If the start of Task B is delays, what is the completion date of the project
A.April 25.
B.Not enough information provided to calculat
C.April 20.
D.April 10.