Near the end of your last project,additional requirements were demanded by a group of stakeholders when they learned they would be affected by your project.This became a problem because you had not included the time or cost in the project management plan for these requirements.What is the BEST thing you can do to prevent such a problem on future projects ?()
A.Review the WBS dictionary more thoroughly,looking for incomplete description
B.Review the project charter more thoroughly,examining the business case for“holes”.
C.Do a more thorough job of contract plannin
D.Pay more attention to stakeholder managemen