问题 单项选择题

Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other.______is following the process-Estimate Activity Durations.

A.Develop Schedule

B.Estimate Activity Resources

C.Define Activities

D.Sequence Activities

答案

参考答案:A

解析:项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是答案A计划编制。

填空题
判断题