A project manager is managing a fixed price(FP)contract.She thinks that a large customer-requested change might impact the schedule of the project.What should she do FIRST ?()
A.Meet with the stakeholder
B.Meet with the tea
C.Renegotiate the remainder of the contrac
D.Follow the change control syste
答案
参考答案:D
解析:
项目经理在管理一个固定价格合同,她认为客户很大的变更请求将影响到项目进度。她首先应该做什么 A) 会见干系人。 B) 会见团队成员。 C) 就更新的合同重新谈判。 D) 遵循变更控制系统。