问题
单项选择题
How should change management be planned for ?()
A.Changes are generally not predictable,therefore planning for change management cannot be sensibl
B.Planning for change management should be done while the various change control processes are being applie
C.Change management can be planned in a set of management plans or a specific change management pla
D.Changes are a sign of bad planninOne should avoid changes during a project thus eliminating the need to manage the
答案
参考答案:C
解析:
变更管理该如何计划 A) 变更通常是不可预测的,因此规划变更管理不明智。 B) 当有不同的变更控制过程被应用时,必须要规划变更管理。 C) 变更管理可以随着一系列管理计划而规划,也可以单独进行规划。 D) 变更是规划作得不好的信号,应该在项目执行中避免变更,也就消除了管理它们的需要。