You are looking at the following data.Project A has a CPI of 0.8 and SPI of 1.2 and EV of 450.Project B has CPI of 1.2 and SPI of 0.8 and EV of 650.Which of the following statement is true ?()

A.Project B is performing better because it has a higher earned valu

B.Project A has schedule slippage and project B is ahead of schedul

C.Crashing project A is a good optio

D.Crashing project B is a good optio

答案

参考答案:D

解析:

你在看下列数据。项目A的CPI是0.8,SPI是1.2,EV是450;项目B的CPI是1.2,SPI是0.8,EV是650。下列哪个说法是正确的 A) 项目B业绩比较好,因为它的EV比较高。 B) 项目A的进度落后,项目B进度提前。 C) 赶工项目A是不错的选择。 D) 赶工项目B是不错的选择。 项目B成本节约,进度落后,需要做进度压缩。