The client demands changes to the product specification that will add only two weeks to the critical path.Which of the following is the best thing for the project manager to do ?()
A.Compress the schedule to recover the two week
B.Cut scope to recover the two week
C.Consult with the sponsor before taking any actio
D.Advise the client of the impact of the chang
参考答案:D
解析:
客户提出对产品的变更,这将增加两周到关键路径上。下列哪项是项目经理最应该做的 A) 压缩进度2周。 B) 削减项目范围来减少2周。 C) 在采取任何行动之前向出资人征求意见。 D) 告诉客户这个变更的影响。 当有变更时,首先评估影响,然后再考虑行动。