问题 单项选择题

The project is not completed until ().

A.the project scope is completed,administrative closure is completed and payment is received

B.formal acceptance is received,and any other requirements for project closure as stated in the contract are met

C.the customer is satisfied and final payment is received

D.lessons learned are completed

答案

参考答案:D

解析:

项目还没有完成,直到______。 A) 项目范围完成,管理收尾也完成,支付的费用已收到 B) 已被正式接受,合同中其他项目收尾的需求都已经被满足 C) 客户满意,最终的费用已经收到 D) 经验总结被完成 按照收尾流程:正式接受成果、经验总结、资源遣散。在这里选择最后的活动。