The project manager has just received a change from the customer that does not affect the project schedule and is easy to complete.What should the project manager do FIRST ?()
A.Make the change happen as soon as possibl
B.Contact the project sponsor for permissio
C.Go to the change control boar
D.Evaluate the other components of the“triple constraint”.
答案
参考答案:D
解析:
项目经理刚接到来自客户的变更,这将不会影响项目进度并且容易完成。项目经理应该首先做什么 A) 尽快让变更发生。 B) 联系项目发起人获得许可。 C) 去变更控制委员会。 D) 评估“三角形约束”的其他因素。 当有变更时首先评估变更的影响。