问题 单项选择题

Which of the following is the most common non-behavioral reason for projects being completed behind schedule and going over budget ?()

A.Selecting a wrong person as the project manage

B.Selecting a wrong person as the sponso

C.Accepting a high-risk projec

D.Inadequately defined requirement

答案

参考答案:D

解析:

下列哪项是最常见的导致项目进度落后、成本超支的非行为原因 A) 选择了错误的人当项目经理。 B) 选择了错误的人当发起人。 C) 接受了高风险的项目。 D) 不适当的需求定义。 需求如果没有定义好,范围如果不明确,会导致项目出最大的问题。