A team member notifies the project manager that the activities comprising a work package are no longer appropriate.It would be BEST for the project manager to be in what part of the project management process ?()
A.Corrective actio
B.Integrated change contro
C.Monitoring and controllin
D.Project closin
答案
参考答案:C
解析:
项目团队成员通知项目经理某些工作包所包含的活动不再合适。项目经理此刻在哪个项目管理过程组内 A) 纠正行动。 B) 整体变更控制。 C) 监视与控制。 D) 项目收尾。