问题 单项选择题

在窗体中添加一个名称为Command1的命令按钮,然后编写如下事件代码:
Private Sub Command1_Click( )
Dim a(10,10)
For m=2 To 4
For n=4 To 5
a(m,n)=m*n
Next n
Next m
MsgBox a(2,4)+a(3,5)+a(4,5)
End Sub
运行窗体后,单击命令按钮,MsgBox中应输出( )。

A.23

B.33

C.43

D.53

答案

参考答案:C

解析: 本题中二维数组a,在二重循环中为数组部分进行了赋值。本题中最后使用到的二维数组的元素值为两个下标之积。所以本题结果为43。

完形填空
Our English teacher was like a friend to us,and we all liked her.One day she came into the
classroom and shouted.“Who did this?”She held up a piece of broken glass and asked,“Who
__1__ the window?”She seldom became angry, __2__ this time she was.
I broke the window.I had done __3__ by throwing a baseball.I didn’t want to admit(承认)
It __4__ I didn’t have enough money to pay for a big window like that.“My father will be __5__,”I thought.At first I didn’t _6_ my hand,but later something strong in my heart
suddenly made me stand up.“I did it,”I said __7_.How difficult it was for me to say that!
My teacher __8__ a book from one of our book shelves and then began walking __9_ my desk. I was afraid that she was going to punish(惩罚)me.
“I know you like collecting __10__ very much,”she said,looking down at my __11__ face.
“Here is the hook about collecting stamps that you are looking for.Now,the book is__12__ and I shall not punish you.Remember,it’s because you _13_ the truth.”
I couldn’t believe it ! My teacher wasn’t punishing me.I didn’t _14_ to pay for the broken window. And I got my favorite book!
As time goes, the book is _15_,so is my wonderful teacher.But I will never forget the lesson the teacher gave me that day.
小题1:
A.cleanedB.climbedC.brokeD.mended
小题2:
A.andB.butC.soD.or
小题3:
A.themB.oneC.thatD.those
小题4:
A.becauseB.ifC.whenD.though
小题5:
A.pleasedB.excitedC.frightenedD.angry
小题6:
A.put onB.put upC.put outD.put away
小题7:
A.terriblyB.honestlyC.easilyD.hardly
小题8:
A.readB.wroteC.tookD.bought
小题9:A. towards         B. opposite         C, against           D. behind
小题10:
A.booksB.desksC.stampsD.windows
小题11:
A.nervousB.prettyC.happyD.square
小题12:
A.youB.yourC.yoursD.yourself
小题13:
A.talkedB.spokeC.saidD.told
小题14:
A.likeB.wantC.useD.need
小题15:
A.openedB.goneC.leftD.closed
问答题 案例分析题

某水利水电工程项目的原施工进度网络计划(双代号)如图1F420151-6所示。该工程总工期为18个月。在上述网络计划中,工作C、F、J三项工作均为土方工程,土方工程量分别为7000m3、10000m3、6000m3,共计23000m3,土方单价为15元/m3。合同中规定,土方工程量增加超出原估算工程量25%时,新的土方单价可从原来的15元/m3下降到13元/m3。合同约定机械每台闲置1天为800元,每月以30天计;C、F、J实际工作量与计划工作量相同。施工中发生如下事件:事件1:施工中,由于施工单位施工设备调度原因,C、F、J工作需使用同一台挖土机先后施工。事件2:在工程按计划进行4个月后(已完成A、B两项工作的施工),项目法人提出增加一项新的土方工程N,该项工作要求在F工作结束以后开始,并在G工作开始前完成,以保证G工作在E和N工作完成后开始施工。根据施工单位提出并经监理机构审核批复,该项N工作的土方工程量约为9000m3,施工时间需要3个月。事件3:经监理机构批准,新增加的土方工程N使用与C、F、J工作同一台挖土机施工。问题:(1)在不改变各工作历时的情况下,发生事件1后,施工单位如何调整计划,使设备闲置时间最少,且满足计划工期要求?(2)按事件2新增加一项新的土方工程N后,土方工程的总费用应为多少?(3)土方工程N完成后,施工单位提出如下索赔:①增加土方工程施工费用13.5万元;②由于增加土方工程N后,使租用的挖土机增加了闲置时间,要求补偿挖土机的闲置费用2.4万元;③延长工期3个月。施工单位上述索赔是否合理?说明理由。