问题 单项选择题

单位工程技术组织措施设计中不包括( )。

A.质量保证措施
B.安全保证措施
C.环境保护措施
D.资源供应保证措施

答案

参考答案:D

解析:技术组织措施是指在技术、组织方面对保证质量、安全、节约和季节施工所采用的方法。技术组织措施的制定是在严格执行施工验收规范、检验标准、操作规程的前提下,针对工程施工特点的不同,分别对待,制定出相应的措施。这些措施有:保证质量措施、安全施工措施、降低成本措施、季节性施工措施、防止环境污染的措施。

阅读理解

阅读理解。

                                                                 Tom Is Late          

     It's 7:30 on Monday morning. It's time for Tom to go to school, Classes begin at 7:40, Tom is still 

(仍旧)  in his room. His mother says, "Hurry, Tom. You must be quick or you'll be late." "Mum, where's

 my pencil-box? I can't find it. I can't go to school without (没有) my pencil-box", cries Tom.            

     Look at Tom's room. What a mess! His books are lying all over the room. His football socks are 

on the desk. A kite and soccer clothes are on his bed. Tom's mother comes to help him. She asks Tom 

to put his books away and Tom's pencil-box is under the books on the floor.       

     "You must look after your things, Tom," says his mother.

1. It's 7:30.  It's time for Tom to      __.                 

A. get up                      

B. go home

C.  go to school      

D.  go to play football             

2. With out        _. Tom can't go to school.

A.  the socks  

B.  the pencil-box  

C. the kite    

D. the books

3.  Tom's _        is in a mess.            

A. room      

B. classroom    

C. bed        

D. schoolbag

4. Tom's pencil-boxes                       

A. on the books            

B. in his bag

C.  under the clothes            

D.  under the books

5. Tom's mother comes to      _ .                        

A. play with him                

B. help him.

C. put his books away              

D. put his kite away

单项选择题