Having the client assist in the project planning ______ .
A.is not always recommended since the client does not have adequate knowledge of project management
B.enables better planning since they are familiar with project insights
C.provides only some understanding, but usually the client dealing with the project has only limited authority
D.usually confuses the situation
答案
参考答案:B
解析: 客户参与项目计划的做法 ______ 。 A) 通常不予推荐, 因为客户没有足够的项目管理知识 B) 能够带来更好的计划, 因为他们更熟悉项目内情 C) 能够提供一些互相的谅解, 但是通常介入项目的客户仅有有限权威 D) 通常使局势混乱 项目干系人参与项目规划过程, 有助于达成共识。