Scope definition is ______ .
A) the process of developing a detailed project scope statement as the basis for future project decisions
B) determining the responses needed to perform project activities
C) analysis of activity sequence, duration, and resource requirements
D) a written statement identifying the quality standards relevant to the project
参考答案:A
解析: 范围定义是 ______ 。
A) 用来创建详细的项目范围说明书作为项目未来决策基础的过程
B) 判断执行项目活动所需要的反应
C) 对活动排序、历时和资源需求的分析
D) 标识项目相关的质量标准的书面说明书
选项A是定义范围;选项C是制订进度计划;选项D是规划质量。