On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A.project planning
B.time estimating
C.cost estimating
D.schedule development
答案
参考答案:D