问题 单项选择题

On some projects,especially ones of smaller scope,activity sequencing,activity resource estimating.Activity duration estimating,and (71) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.project planning

B.time estimating

C.cost estimating

D.schedule development

答案

参考答案:D