A typical application of this (71) is ADSL. It is emerging as the technology for home-and small-office Internet connectivity. It provides either 1.5 Mb/s~8 Mb/s from the network to the user and 64 kb/s~512 kb/s in the reverse direction depending on the distance, 12000 or 18000 feet. The different speed for each direction gives it the (72) label. ADSL is designed to take advantage of the fact that video-on demand, telecommuting, and Internet access traffic are inherently asymmetrical. The user (73) a brief message up to the network and receives a ton of data coming back, either a movie or a piece of data download. Under such a scenario, low-speed traffic to the network is just fine. ADSL .delivers high (74) where you need it and only uses a single copper pair. Through multiplexing, it also reserves (75) of the bandwidth for POTS.

A.asymmetric

B.compressed

C.irregularity

D.symmetric

答案

参考答案:A

选择题
问答题

阅读以下关于项目进度管理的说明,根据要求回答下面问题。
[说明]
PH公司是一家系统集成商,杨某是PH公司的一名高级项目经理,现正在负责一个财务管理系统的开发项目。他认真分析了项目的技术特点,并很快组建了自己的项目团队。杨经理对自己的团队很满意,因为这些成员对该项目所采用的技术都很熟悉,且他们都有一定的开发经验。在项目开始的第一个月,项目团队给出了一个粗略的进度计划,估计项目的开发周期为11~16个月。两个星期后,产品需求已经确定并得到了批准,杨经理制订了一个以11个月为期限的初步进度表,项目团队成员对这11个月的进度计划也相当乐观,因为项目的目标已经确定,并且开始书写需求规格说明书,概要设计也已经开始。
杨经理认为,项目的详细进度表在半个月之内就可以提交,因为他以前曾做过一个类似的项目,不用花费太多的时间去制订这个进度表。在接下来的8天里,他努力地制订详细的进度计划。为了让他的项目成员去做一些他们“应该做的”设计、开发等工作,杨经理在做计划时没有让技术人员参与详细进度表的制订。杨经理依据每个人员的最高生产效率和最佳的开发状态来编制计划。经过几天的努力,杨经理给出了详细进度表的草稿,并交付审核。相关评审人员经过评审,给出了如下的意见。
①该计划进度安排很紧张,没有任何多余时间,应引起高度重视。
②这对于用户来说是一个“最合适的”进度计划。
该进度计划还是被通过,并形成了该项目的正式进度计划。当项目团队成员认真分析完这份进度计划后,认为进度太紧张,任务可能无法完成。他们认为目前的项目团队人员太少,也没有充分考虑休假、节日和其他机动时间。除了以上的主要问题外,项目团队成员还提出了一些其他的问题,但基本上没有得到相应的重视。只是为了缓解项目团队成员的抱怨情绪,在报请上级主管批准后,杨经理将进度表中的计划工期延长了5个星期。
1.请用400字以内的文字,结合你的项目管理经验,分析杨经理在进度管理方面主要存在哪些问题