Activity definition involves identifying and documenting the specific activities that must be performed to produce the deliverables and sub-deliverables identified in the work breakdown structure(WBS). All the following statements about the activity list produced as an output from activity definition are true EXCEPT:

A.Activity list must include All activities that will be performed on the projec

B.Activity list may include some activities that are as part of the project WB

C.Activity list should include descriptions of each activity to ensure that the project team members will understand how the work is to be don

D.Activity list is used in the schedule model and is a component of the project management pla

答案

参考答案:B

解析: 活动定义包括识别和记录完成WBS中可交付成果所必须要执行的活动。所有下列关于活动定义过程的输出活动列表的说法都是正确的, 除了: A) 活动列表必须包括项目中所有需要执行的活动。 B) 活动列表包含的一些活动是WBS的组成部分。 C) 活动列表应该包括每个活动的描述以确保项目团队成员明白如何完成这些工作。 D) 活动列表用于进度模型中, 是项目管理计划的一部分。 活动列表不是WBS的组成部分,活动清单是独立的成果,描述为了获得项目工作包需要进行的必要的活动。选项D是04版书上原文。